3. Having confirmed that the technical parameters of the same equipment offered by M/s Sudhir and M/s Trishul Enterprises matched perfectly, the MC negotiated terms of payment to the potential suppliers. The costs negotiated with M/s Trishul Enterprises and the payment of last Rs 1, 35, 000/- in three monthly installments offered a more advantageous deal for the Society and was concluded after making an open offer to anyone who could get the Society a better deal. The offer letters from the dealers and relevant documents / records are available in the Society office for anyone wishing to examine the same.
4. The installation of the new 200 KVA DG was completed on 10 Nov 2009 and work to provide connections to individual homes is scheduled between 12th Nov to 15th Nov 2009. Since central procurement of equipment in bulk makes better economic sense, members / residents were offered the connection from the Electric Sub Station (ESS) to their respective flats @ Rs 2000/- per flat. Thus far 58 members have applied for the same and are being given the power backup at the rates quoted above.
5. It may please be noted that although power backup to flats will remain open even after 15th Nov 2009, the rates are likely to vary substantially. Members, who are yet to apply for power backup, may like to avail of the opportunity now rather than having to pay much more for the facility at a later stage.
6. Last date for accepting the request for power backup facility for individual flats at the current rates is 14th Nov 2009.
This is an interesting development. Even though members have to pay Rs 200.00 per month for this service, the real estate cost of flats in Din CGHS seems to have gone up by 10 lakh in the open market. Good. Please keep up the good work. Thank you.
ReplyDelete